200kVA Crane Aviation Light Hybrid Power Solution

green-power-hire

200kVA Crane Aviation Light Hybrid Power Solution

Solution Information

Above is an example of a hybrid power solution combining a 200kVa diesel generator with one of our 45kVa 45kWh battery storage systems.

In this example we are running the generator to power the crane directly between the hours of 7am - 6pm Monday - Friday and Saturday 8am - 2pm. The battery controls the generator automatically based on these site operating times but outside of these hours the battery keeps power to the crane aviation light and hydraulic fluid heaters on the crane. This solution delivers a reduction in generator run time of almost 64%.

As you can see the generator has 2 outputs, the first is connected directly to the crane powering it directly all day. When the generator is turned off power to the crane is automatically lost.

The second generator output is connected to the battery system which feeds the essential overnight loads such as the crane aviation light. Although the battery requirement is small we are delivering a huge reduction in generator run time.


System Benefits

The real benefits of the Green Power Hire system based on a 28 day period

System Comparison

How our system compares against the rest based on a 28 day period

Hybrid Power System

  • Fuel consumption - 8784.0L
  • Silent run hours - 428
  • C02e emissions - 27.72
  • Generator run hours - 244

Diesel Generator

  • Fuel consumption - 18953.3
  • Silent run hours -0
  • C02e emissions - 59.82T
  • Generator run hours - 672
 